top of page

B&M BEDFORD DISTRIBUTION HUB

Project: B&M BEDFORD DISTRIBUTION HUB

Subject: DISPUTE RESOLUTION REPORT

Value:  Infrastructure & Earthworks Package, £18M

Area: Specialist Commercial & Technical Consultancy Services

​Client: Due to the sensitive nature of our work we do not reveal the name of our client

Achievements: Successfully protected and promoted the commercial interests of our client.

 

Main Deliverables:

  • Preparation of Technical Note regarding the earthworks carried in relation to B&M Bedford distribution Hub

  • Settled dispute

Work Items

  • Validate the ‘as built bulk earthworks’ against the cut and fill model.

  • Review sequencing of the cut and fill operation as works progressed

  • Review the locations of suitable material, the earthworks model suggested that suitable material should be easy to located but there was a dispute regarding this

  • Establish the quantity of existing clay within the building footprint

  • Establish where the suitable material was placed or was it mixed in with unsuitable resulting in it becoming unsuitable

  • Review the quantity of clean stone placed in the external yard as a result of the formation not reaching specification (both displacement and replacement), then the corresponding material relocated to bunds or disposed off site.

  • Review the quantity of clean stone placed around specific gridlines

  • Establish the quantity of stone imported to the building footprint

  • Preparation of final Cut and Fill Tables (Earthworks)

  • Preparation of final Quantity Tables (Infrastructure and Civil Works)

  • Preparation of final Models to present design and As-Build positions

  • Review and assess opposition’s party position

  • Settle dispute

bottom of page